Rerailing Equipment for Concrete Bullets

The concrete bullets used to transport concrete to the shutters underground each carry 15m3 of concrete and have the gross weight of 50tonnes.

The site mechanical team designed and built a system to re-rail a fully laden load back on to the tracks.

Trials have shown this is a very effective system to re-rail heavy trains in confined spaces removing personnel from the area during the rerailing.

Historically rerailing construction trains in tunnels has involved the tunnel workers around the equipment in confined spaces with potentially uncontrolled loads. The new system that has been developed does not require people to be close to the equipment as it is re-railed.

Footer Reference

Monitor Report. Tideway. London. October 2022.


Did you find this article helpful?

Please rate this article

0 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 5 (0 votes, average: 0.00 out of 5)
You need to be a registered member to rate this.
Loading...

Leave a comment

Return to previous page

The Scheme does not promote or endorse any products, goods or services. For more information, click here.

Best Practice Hub
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible.

Cookies are small pieces of text sent to your web browser by a website you visit. A cookie file is stored in your web browser and allows the site or a third-party to recognise you and make your next visit easier and the website more useful to you.

Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

We only use cookies to improve your experience and monitor web traffic. All data we collect on this site is anonymous and not shared or sold. Please find more information here

The Best Practice Hub is provided by the Considerate Constructors Scheme