This contractor have produced a scaffold schedule in 3D so they can visualise each lift of scaffold and appreciate how it interacts with the crane, hoist, and loading bays.
This has enabled their planning phase to identify risks that were otherwise not appreciated until viewed in 3D.
It also enables them to communicate their scaffold complexities to other trades.
Entry submitted by Westridge Construction