The Dundee Regional Performance Centre for Sport have been developing an approach to using BIM to review that installed services have been installed correctly and in the correct location.

The project team have been using a 360 camera to record installed service before ceilings go up. Linking them into the BIM model allows the team to review what the M&E Subcontractor has installed to specification, and where changes have taken place on site, these need to be updated in the model.

This approach provides our customer with evidence and confidence that services are in the correct location.

This data can then be used in the future to improve any future maintenance procedures.

Footer Reference

Entry submitted by Balfour Beatty


Did you find this article helpful?

Please rate this article

0 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 5 (0 votes, average: 0.00 out of 5)
You need to be a registered member to rate this.
Loading...

Leave a comment

Return to previous page

The Scheme does not promote or endorse any products, goods or services. For more information, click here.