On IQL S9 we have implemented a moat exclusion zone system of Heras fence ‘Zones’. Each zone, installed around the perimeter of the building, is 5x5m with a lockable gate.

To access a zone the contractor has to fill out a permit, detailing the works being carried out, which is then signed off by Lendlease allowing entry. When a zone is booked out the two adjacent zones cannot be booked out by different contractor, providing a 5m exclusion either side of the work area and vertically up the floors of the building.

This enables works along the perimeter of the structure such as facade installation, safety screen install and any high risk lifting out through moats to be carried out safely.

Footer Reference

Entry submitted by Lendlease


Did you find this article helpful?

Please rate this article

0 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 5 (0 votes, average: 0.00 out of 5)
You need to be a registered member to rate this.
Loading...

Leave a comment

Return to previous page

The Scheme does not promote or endorse any products, goods or services. For more information, click here.

Best Practice Hub
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible.

Cookies are small pieces of text sent to your web browser by a website you visit. A cookie file is stored in your web browser and allows the site or a third-party to recognise you and make your next visit easier and the website more useful to you.

Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

We only use cookies to improve your experience and monitor web traffic. All data we collect on this site is anonymous and not shared or sold. Please find more information here

The Best Practice Hub is provided by the Considerate Constructors Scheme