The contractor has greatly removed leading edge work through modular lift installation which means the only time gates are open is when the lift car is in position.
The lifting point is pre-installed and tested at ground level prior to capping slab install. This brings a time saving of approximately 2 hours per module to install.
There is a reduction of material storage on site as the unit is installed upon delivery. There is also a reduction in deliveries and less chance of damage as materials not being moved or left laying around site.
Information provided by Laing O'Rourke