The remote location of the noise and dust monitors on this project required a power source to be installed.

Solar alone would not be sufficient to power them and a diesel generator used finite fossil fuels, therefore they combined a hydrogen cell with solar panels to provide enough power to run the monitors 24/7.

The hydrogen used can be created from a completely renewable source and therefore the whole system doesn’t require the use of finite resources such as fossil fuels.

The hydrogen generator also only produces the demanded power unlike a diesel generator therefore power is not wasted due to a diesel generator having a minimum idle power level that isn’t fully utilised.

Footer Reference

Information provided by Keltbray Ltd


Did you find this article helpful?

Please rate this article

0 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 5 (0 votes, average: 0.00 out of 5)
You need to be a registered member to rate this.
Loading...

Leave a comment

Return to previous page

The Scheme does not promote or endorse any products, goods or services. For more information, click here.

Best Practice Hub
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible.

Cookies are small pieces of text sent to your web browser by a website you visit. A cookie file is stored in your web browser and allows the site or a third-party to recognise you and make your next visit easier and the website more useful to you.

Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

We only use cookies to improve your experience and monitor web traffic. All data we collect on this site is anonymous and not shared or sold. Please find more information here

The Best Practice Hub is provided by the Considerate Constructors Scheme