Remote Movement Monitoring System

Published 9 January 2023 | Written by Jack Endean
CategoriesControls Inspection and assurance

The Geo-Sense remote movement monitoring system has been installed to the rear (water) side of an existing dock wall, situated under a suspended quay structure. The technology relays data wirelessly in 5 minute intervals, measuring movement in the X,Y,Z axis, providing information of the impact of the adjacent works. Using this technology in what would otherwise be an area only…


Asbestos Recycling Scheme

Published 9 January 2023 | Written by Jack Endean
CategoriesConsultation Protect the local environment Specialist input

This regeneration brownfield project required the demolition of several industrial units, this led us the contractor look into how they recycle materials such as the sheet asbestos product on the roofs. Recycling demolition asbestos is a new idea and this site was the first in the United Kingdom to use use this process. Using this method required meticulous planning to…


Working at Height – Mobile Restraint Solution

Published 21 October 2022 | Written by Jack Endean
CategoriesPositive reinforcement for good safety practices Risk assessments

To deliver long welded rail to site, a specialised rail fleet provided by Network rail is required. Availability of these trains is limited which was preventing efficient programming of works. An older long welded rail delivery train (LWRT) had been mothballed due to no protection to staff working at height but offered an opportunity to resolve the delivery problem. To…


Vacuum Sucker for Lifting Precast Concrete Panels into Position

Published 21 October 2022 | Written by Jack Endean
CategoriesModern methods of construction

The building on this project was designed with precast concrete cladding panels on the ground floor. The first floor overhangs the ground floor envelope, which meant the panels could not be lifted from above. So in order to maintain the programme and resolve the installation challenge, the contractor worked with a lifting specialist to develop a vacuum lifting device normally…