The project was the result of an assessment of the floodwall in Woodbridge during the tidal surge of December 2013, when the water came within 800mm of the top of the defences.
Site Manager Ashley Tate explained:
“When the water receded, the wall showed signs of excessive movement, so an investigation was undertaken to determine the stability of the wall. Analysis showed that had the water level been 200mm higher the wall would have overturned and failed. Hence a design was produced to rebuild and strengthen the wall in order for it to continue to provide a high level of protection to the town.”
The work, on behalf of client the Environment Agency, involved driving steel-cased piles approximately 8m deep into the footpath that runs on the river side of the floodwall.
Ashley explained:
“These are to support a new 300mm thick reinforced concrete slab to anchor and strengthen the existing sheet pile defence.
“The slab doubles up as the reinstated footway. A new brickwork face was then built on the slab in front of the sheet pile wall and concrete placed to form the core of the new wall. A precast coping was then fixed to the top of this to bring the wall up to the desired defence level.
“The work was over a 265m long stretch of the riverbank and was split into two phases so that could be maintained to various boat clubs who had buildings along the river. The overall duration of the works is nine months.”
The Scheme champion prepared a CCS folder with divisions for each part of the Code of Considerate Practice, with ideas of best practice taken from its own sites and the Best Practice Hub. This folder also provided a means of recording what had been done to incorporate the requirements of the Code into its operations.
The site is on the Woodbridge Waterfront, an amenity area frequented by both local residents and tourists. There is a rowing club, two boat yards, a busy tearoom, boat moorings and a public car park that are affected by the works. Access is down a narrow road through a residential area.
You can find out how the Jackson Civil Engineering project team addressed these challenges and carried out best practice initiatives to comply with the Considerate Constructors Scheme by clicking on the sliders below:
CRASH Charity introduces construction companies to charitable projects to create lasting social
The A14 Cambridge to Huntingdon improvement scheme is a £1.5 billion roadworks project including a
When Project Partners were asked by Truro-based ISO Spaces to fit out shipping containers they
In the construction industry, approximately 3,700 cancer cases arise as a result of exposure to
As a regulated charitable housing association, London and Quadrant’s (L&Q) culture is deeply