The VBA Ltd joint venture team is future-proofing the market town of Louth in Lincolnshire from flooding, being the first flood control project in the country to use the Hydroslide – a new technology in flood defence which controls water deluge.
The joint venture comprising VolkerStevin, Boskalis Westminster and Atkins is part of the Environment Agency’s Water and Environment Management (WEM) Framework.
The Louth Flood Alleviation Scheme will reduce the risk of flooding to the town of Louth by the construction of two dams which are homogenous earth-filled embankments. The embankment of the north storage area will measure 150m and the one in the south will measure 200m. These storage areas will reduce the risk of flooding to 355 local properties from the River Lud.
Outlining the project, VBA VolkerStevin Site Manager, Matthew Parkinson said:
“There have been several recorded flood events within Louth, with the primary source of flooding being associated with heavy rainfall. However, it has also been known to flood as a result of surface water and combined overflow systems (this is the responsibility of LCC and Anglian Water respectively).
“Risk to life, property and infrastructure are predominantly concentrated in the town of Louth itself, where the most severe flooding events occurred in 1920 and most recently in 2007. This scheme will see two flood storage areas constructed outside the town. The first will be located off the A157 and the second off Halfpenny Lane, both adjacent to the A16.
“Both of the Louth Flood Alleviation schemes are part of a ‘Design and Build’ framework agreement for the Environment Agency. The beauty of schemes like these is that the construction process is discussed and planned alongside the design. This means that as a site team and a design team, we can work in collaboration to produce a final design that not only meets the client’s requirements, but meets the needs of the contractor in terms of buildability.
“The scope of works included building a flood storage structure to control the flow of water through the town of Louth and providing a flood storage area where storm water could be retained and released over time.”
Control Structure
The Control Structure is a precast concrete shaft made up of seven 1m rings containing fourteen segments with an internal diameter of 7.5m. Inside the shaft is a diaphragm wall and flow control device. The device is known as a Hydroslide and is basically a float valve with a blade that shuts the watercourse down and throttles the flow to a rate at which the downstream networks can manage without flooding.
The Hydroslide is a new technology in flood defence and this is the first time one has been used in a flood control environment in this country. The main benefit to using this new technology is the control this device offers. Using the Hydroslide has meant that the flood storage level has been reduced by approximately 1.0m. This has avoided installing an additional 5000 tonnes of clay embankment.
The dams
The height of the dams will be around 6m, retaining a combined volume of 213,000m3 of storm water during a flood event. Both storage areas fall under the requirements of the Reservoirs Act 1975.
The northern and southern storage areas are both located immediately upstream of Louth’s bypass. The design is for two stand-alone impounding embankments. The fill material for the sites is clay from borrow pits within the flood storage area.
Construction process – Louth North and South
Construction commences with the installation of a reinforced concrete base, inlet and outlet box culverts, and a precast concrete shaft with cover slab. The shaft is divided by a reinforced concrete wall and the flow is controlled through an opening in the wall by a Hydroslide. Upon completion of the structure the earthworks will commence, taking clay from borrow pits within the site and placing this in layers to construct the dam across the valley. Further to these works, the site will have service and access roads for the client and landowners, landscaping, and an automated weed screen cleaner.
Here are some examples of best practice initiatives carried out by VolkerStevin:
CRASH Charity introduces construction companies to charitable projects to create lasting social
The A14 Cambridge to Huntingdon improvement scheme is a £1.5 billion roadworks project including a
When Project Partners were asked by Truro-based ISO Spaces to fit out shipping containers they
In the construction industry, approximately 3,700 cancer cases arise as a result of exposure to
As a regulated charitable housing association, London and Quadrant’s (L&Q) culture is deeply