Tensar Geogrid

To minimise excavation for both the piling mat and the haul road, Tensar geogrid was utilised to create a mechanically stabilised layer beneath these areas.

This approach eliminated the need for a 600mm dig-off for the piling mat ,instead the Tensar was laid directly over the existing topsoil, allowing the construction layers to be built up from there.

The same principle was then successfully applied to the temporary haul road, further reducing material use, vehicle movements, and associated carbon emissions.

By using Tensar within the road construction, they achieved a carbon saving of 3,820 kg CO2e, while the use of Tensar within the piling mat contributed an additional 6,570 kg CO2e reduction.

To find out more, click the link below.

Go to resource


Footer Reference

Information provided by Tilbury Douglas


Did you find this article helpful?

Please rate this article

0 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 50 votes, average: 0.00 out of 5 (0 votes, average: 0.00 out of 5)
You need to be a registered member to rate this.
Loading...

Leave a comment

Return to previous page

The Scheme does not promote or endorse any products, goods or services. For more information, click here.

The Best Practice Hub is provided by the Considerate Constructors Scheme