taxonomy.php

Adequate lighting

Green Flood Lights

This contractor has taken the approach to install green flood lights as an alternative to traditional white lights on site. This has the benefit of being much more wildlife friendly by reducing the impact on the night vision of animals. Green lights have a lower ambience which also reduces the impact on neighbours as well as bringing a reduction in…


Sunlight Simulation for Neighbours

As the scaffold on this project has resulted in the blocking of natural light into the canteen area of a neighbouring property, the team arranged for a semi translucent window film to be fitted which when backlit would simulate a warm sun glow into the area. This was well received and aided the wellbeing of the workforce in the neighbouring…


The Light Balloon Module System

Works were being carried out for the removal of existing street lighting on the A34 and A555. To ensure there was adequate lighting for the travelling members of the public and the workforce carrying out night work activities, an alternative light source was required. After some research and a trial period the Light Balloon Module system was found to be…


LED Lighting installed on a motorway

We completed £1.1m of lighting improvement work on the M62 over a 19km length between J22 Saddleworth Moor and Kirklees Viaduct, west of Junction 25. We replaced over 1,000 high pressure sodium lanterns with new LED lighting units; this solution was devised by the contractor to suit the client specification. These require no routine maintenance, eliminating the need for cyclic…


FHOSS Halo System

Vehicle movements are without a doubt a risk to the health and safety of the workforce on any construction site. Particularly with darker mornings and evenings during the winter months where visibility is significantly reduced. The FHoss system provides illuminated walkway systems and crossings to enable a safe passage for operatives and improved visibility for drivers. Focused beams of light…


Powertrack Low Level Modular System

On this project they have strived to find new products and ways to ensure that they increase safety, efficiency, sustainability and cost effectiveness. One product they have found is Powertrack, which is a low-level modular system which distributes lighting and power across construction sites, its made up of eleven profiles that can be moved and modified in minutes. They estimated…


Rechargeable Temporary Lighting

Whilst waiting for our temporary lighting to be installed we purchased eight portable and rechargeable LED light units with motion sensors were fitted. Each light fitting has four settings which allows different levels of light for different tasks being undertaken. They are small and compact and once fully charged they have a battery life of up to five hours and…


LED Stop and Go Boards

The site have incorporated LED illuminated manual stop and go boards. These provide many benefits starting with greatly improved visibility and hence safety for operatives. The ability to respond quickly and efficiently to reported problems, particularly at night when the system is combined with halo-light fitted hardhats, increases road safety for all. This is an improvement to a long standing…


Efficient Alternative to Individual Lighting Towers

Sites that are not on a mains electricity supply often use individual lighting towers, each powered by a single generator, to provide lighting to site compounds etc. This can result in relatively high fuel use and associated carbon emissions. Volker Fitzpatrick chose instead to install a number of second hand street lighting columns, fitted with LED lights, linked to the…


Ejector Dumpers

The Ejector Dump Truck is being used on the M20 Junction 10a Project. The positives of the CAT 730 C2 EJ that is in use on the project include: New operator controls: advanced traction control system and a new stability-assist system. A fuel-saving ECO operating mode and modification that reduce empty weight by 22%. These features combine for an up…


Microwave Sensors on Temporary Lighting

As part of an ongoing effort to minimise carbon dioxide emissions, Multiplex, working in collaboration with Cape (Electrical & Mechanical) has successfully procured the use of microwave sensors within the temporary LED lighting package at the Marble Arch Place project. There are many advantages to using microwave sensors over traditional head-end controlled and passive infrared sensors (PIR) temporary lighting systems….


Green Light to Highlight Tunnel Refuge Points

Construction work in confined spaces, such as tunnels, poses a unique risk to those working on site. One of these risks is the danger of collision between pedestrians and plant machinery. The project team identified the Plant Pedestrian interface within the tunnels to be a high consequence risk. Refuge bays exist in the tunnels to minimise the risk of collision…


Pulsar Pro LED lighting

Safety is of utmost important on sites, particularly those in close proximity to dangerous areas like roads and rail track. Good lighting is essential to operative safety to increase visibility. We used the Pulsar Pro multi-mode, rechargeable LED warning light for traffic control, signalling, hazard awareness, zone demarcations and vehicle safety. These small units are manufactured in shock-resistant plastic, and…


Best Practice Hub
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible.

Cookies are small pieces of text sent to your web browser by a website you visit. A cookie file is stored in your web browser and allows the site or a third-party to recognise you and make your next visit easier and the website more useful to you.

Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

We only use cookies to improve your experience and monitor web traffic. All data we collect on this site is anonymous and not shared or sold. Please find more information here

The Best Practice Hub is provided by the Considerate Constructors Scheme