Willmott Dixon Construction’s project involved the construction and internal alterations of discrete adult and children Emergency Department facilities, all requiring a highly sensitive approach to construction.
This was achieved to exceptional levels by the use of clinical screens, dust mats, acoustic blankets for the cutting zone, dust suppression, extraction units and collected rainwater. Heavy works were also programmed at specific times.
The project comprised a new extension to the current A&E facilities at the hospital which were completely remodelled. Two new buildings – one of which was 2.5 storeys high – were constructed, as well as a single-storey paediatric entrance and waiting area.
Outlining the challenges of construction in a working hospital, Site Manager Jeff French said:
“Having worked in a hospital environment for the last two years we have had to learn to adapt to the challenge this brings. It is imperative that certain activities remain unaffected at all times. The general public are more vulnerable due to the nature of their visits, either physical or mental, and this has to be considered at all times.”
The project team were also tasked with remodelling three large internal wards, one of which was the previous A&E Department. Great consideration was given towards the operational policy of the hospitals, including working alongside the ‘Blue Light Team’ and liaising with the fracture, endoscopy and other departments to ensure normal operations remained uncompromised.
Explaining the challenges of this specialist work, Jeff said:
“The logistics of the project and working within the layout of the site have been difficult. We only had access to the front of the project and had live wards on three sides, so building techniques and programming had to be carefully considered. Noise and dust have been key drivers throughout the project and we have had to sit with the supply chain and consider the working hours, activities and techniques employed to reduce the risk.”
During the first phase of the works, site-wide infrastructure had to be installed to bring services and supplies to facilitate the work reconfiguring the wards. New structural steel works and drainage alterations meant that the team had to operate in small closed-off sections and work to tight deadlines. A temporary ambulance entrance also had to be created to service the new works and allow the smooth transition of Phase Two which commenced, three weeks after the completion of Phase One.
Phase Two entailed the removal of asbestos from the existing A&E Department and the demolition of the front of the building, as well as a separate building. This was all carried out while the team stripped out and reconfigured the existing A&E Department.
You can find out how the team rose to the unique challenges of this project and read about the examples of best practice implemented by Willmott Dixon to comply with the Considerate Constructors Scheme by clicking on the sliders below:
CRASH Charity introduces construction companies to charitable projects to create lasting social
The A14 Cambridge to Huntingdon improvement scheme is a £1.5 billion roadworks project including a
When Project Partners were asked by Truro-based ISO Spaces to fit out shipping containers they
In the construction industry, approximately 3,700 cancer cases arise as a result of exposure to
As a regulated charitable housing association, London and Quadrant’s (L&Q) culture is deeply