Red Light to Inform Operatives that Hoist is Out of Service

Published 1 March 2021

On this project they have 13 car hoist, covering 6 building and basement areas, and they have


Rainwater Harvesting and Wheel Wash

Published 1 March 2021

This project has implemented a water saving measure which seems obvious in retrospect and is


Mood Meter

Published 1 March 2021

The coronavirus pandemic and lockdown has had a marked effect on people’s mental health. The Lack


Interactive Mapping used to help with Communications

Published 1 March 2021

The Hawick Flood Protection Scheme is split into 42 work sections for delivery. With the River


First Response Emergency Care Site Responder

Published 1 March 2021

This project have a trained Level 3 First Response Emergency Care (FREC3) Responder on site to


Community Information Signs with QR Codes

Published 1 March 2021

To keep local residents and businesses updated regular newsletters are sent out via email. In


Net Zero Carbon Challenge

Published 1 March 2021

The Net Zero Hackney Challenge was a programme, developed by the project team aiming to educate


Recycled and Reusable Plastic Pallets

Published 1 March 2021

A continual issue found on construction sites, from both an environmental and health and safety


Working Conditions Survey as Part of a Modern Slavery Strategy

Published 22 February 2021

As part of the contractors strategy to help eradicate modern slavery, one of the projects conducted


WaveWalker

Published 22 February 2021

The WaveWalker is a modified jack up barge, which is capable of manoeuvring under its own power and


Use of Drone Mounted Camera and Thermal Imaging to Detect Skylark Nests

Published 22 February 2021

This project is situated on a large greenfield site with surrounding woodland and is an ideal site


Special Needs Local School Catering for the Site

Published 22 February 2021

The contractor were keen to make links to the local surrounding schools and charitable


Services Avoidance and Surveying Equipment

Published 22 February 2021

This contractor has put into use new services avoidance and surveying equipment the Leica DD


Precast Floor ‘U-Slab’

Published 22 February 2021

An opportunity arose to demonstrate a bespoke integration of structure and MEP services during the


Pre Serviced Walls

Published 22 February 2021

On this project they are using pre serviced walls across several of the floors. These are walls